Request/Subject
Approval of Amendment No. 1 to Contract No. 032712-1 with Visus Engineering Construction
Background Information
On September 18, 2012, Gila County entered into a contract with Visus Engineering for adding some turn lanes at Russell Road, Besich Blvd. and Hope Lane, to improve roadway safety. The contract was issued through the Formal Bid process. Gila County requested proposals for this work and signed a contract with the lowest qualified bidder, Visus Engineering Construction, Inc.
 
The contract amount is $720,000. Included in the $720,000 contract amount is $75,000 for Force Account Work. (See attached Visus Bid Schedule, Item No. 109). The Force Account item is to be used as a contingency item for unforeseen extra work that may be required to complete the project.

The following documents are attached to this Agenda Quick item; Gila County Request for Invitation for Bids-Russell Road Reconstruction Project-Bid Call 032712-1; Gila County Contract No. 032712-1; Visus Bid Schedule with the unit prices that the project was contracted off of; a Cost Overrun and Underrun Explanation; a copy of executed Change Orders #1 through #10; CLW Memo regarding Change Order Explanation - 1; CLW Memo regarding Change Order Explanation - 2; and a copy of Amendment 1 to Contract No. 032712-1 with Visus Engineering Construction.
Evaluation
There are ten (10) change orders totaling $121,157.86 that were extras related to the project, but not included in the bid items.

Change Order #1 was for New 4" PVC fiber optic conduits requested by Gila County- $17,666.97
Change Order #2 was for New waterline changes requested by Arizona Water Company - $19,549.05
Change Order #3 was for Lowering of a 1" gas sewer service which was in conflict of the new parking lot - $1,243.79
Change Order #4 was for Excavating and lowering of a 4" communication conduit, water service and relocate backflow preventor - $1,702.68
Change Order #5 was for Pothole and locate 4" communication conduit, and grade and backfill gas trench - $1,865.93
Change Order #6 was for Removal of existing concrete retaining wall located at the north end of Russell Road - $2,955.44
Change Order #7 was for Installing concrete cap over El Paso Natural Gas line - $22,137.00
Change Order #8 was to Remove an unforeseen subsurface condition, which included removal and backfilling of a cattle guard - $7,715.00
Change Order #9 was to Relocate water services from edge of roadway - $164.14
Change Order #10 was for the balance forward from Change Order #9 and final adjusted quantity overruns/underruns - $46,157.86

All but $46,157.86 of these change orders were included in the Force Account that was pre-approved in the contract. This bid was a unit price bid, not a lump sum bid. During construction the plans may not fit the actual construction so modifications have to be made. There are cost overruns and credits to the bid items totaling $46,157.86.

Attachment, entitled "Cost Overrun and Underrun Explanation" identifies the quantity overruns and underruns on some of the original bid items. 
Conclusion
The original amount of Contract No. 032712-1 was for $720,000. Gila County Public Works would like authorization to increase the contract amount for Contract No. 032712-1 by $46,157.86, for a new total contract amount of $766,157.86, for cost overruns. If authorization is granted, an Amendment is attached to this agenda item for the Board's approval.
Recommendation
Gila County Public Works recommends authorization to issue an Amendment to Contract No. 032712-1 with Visus Engineering Construction, Inc., to increase the contract by $46,157.86 for a final total contract amount of $766,157.86, for the work performed on the Russell Road Reconstruction project.
Suggested Motion
Approval of Amendment No. 1 to Contract No. 032712-1 between Gila County and Visus Engineering Construction to increase the contract amount by $46,157.86 for cost overruns, for a total contract amount of $766,157.86 for work performed on the Russell Road Reconstruction Project.

Attachments
Gila County Request for Invitation for Bids-Russell Road Reconstruction Project-Bid Call 032712-1
Gila County Contract No. 032712-1
Visus-Bid Schedule
Cost Overrun and Underrun Explanation
VISUS COR #1 11-15-12
VISUS COR #2 11-15-12
VISUS COR #3 11-15-12
VISUS COR #4 11-15-12
VISUS COR #5 11-15-12
VISUS COR #6 12-14-2012
VISUS COR #7 12-14-2012
VISUS COR #8 12-14-2012
VISUS COR #9 & #10 2-12-2013
CLW Memo Regarding Change Order Explanation - 1
CLW Memo Regarding Change Order Explanation - 2
Amendment # 1 to Contract #032712-1 with Visus Engineering Construction
Legal Explanation

AgendaQuick©2005 - 2024 Destiny Software Inc., All Rights Reserved