The work consists of a roadway improvement project for a portion of Gisela Road. The proposed project would improve approximately 0.63 miles of the existing roadway west of the summit area. The proposed work consists of pulverizing the existing pavement surface and base material where applicable followed by the installation of new aggregate base material and asphaltic concrete pavement.
The existing surface of Gisela Road is paved; however, due to the age of the pavement, this road requires routine maintenance from County forces.
The Gila County Manager approved a contract on February 8, 2018, for Woodson Engineering to prepare plans and specifications for improvements to Gisela Road.
On August 20, 2018, the Board of Supervisors approved the advertisement of IFB No. 080818. The IFB was advertised in the Payson Roundup newspaper on August 28, 2018, and September 4, 2018. The bids were opened on August 30, 2018, at 4:00 p.m. and there were 6 responses. The bids were opened at 4:00 p.m. and evaluated in accordance with A.R.S. § 41-2533 Competitive Sealed Bidding. |